Excavate the foundation trench in accordance with design specifications and test the bearing capacity of the foundation soil.

 

Implement foundation treatment measures-such as replacement filling, reinforcement, and compaction-to ensure compliance with the required bearing capacity.

 

Level any uneven or sloped rock surfaces using concrete.

 

If the foundation cannot be seated directly on bedrock, it must be embedded at a depth of at least 1.5 meters below the scour line; scour-protection mats shall be laid along the outer perimeter of the foundation.